SH Projects have just completed a fit out project over in Grantham. The area was in need of complete refurbishment and we really wanted to try and freshen up the current area as much as possible and create an inviting new communal area. The works were completed over a tight programme of 11 days, incorporating a complete strip out and refurbishment of the main open space, hallway and toilets. We completed a new kitchenette installation, flooring and decoration in the main room in addition to laying flooring in the hallway. The toilets were freshened up and all the electrics were newly installed.
Working at this time of the year came with its challenges, which meant we needed to plan strategically in order to deliver this project. Credit must go to our delivery team who managed to turn this project around in such a tight timescale, working around a very sensitive live environment.
Completion: November 2021